MAJOR WORKS UPDATE: SUN 5 MAR 2023
Progress Report Cavity flashing works on the Eastern (3-bed) façade are 100% complete.Affected Eastern balcony doors for Units 34, 31 and 28 have been removed and hob works including waterproof …
Progress Report Cavity flashing works on the Eastern (3-bed) façade are 100% complete.Affected Eastern balcony doors for Units 34, 31 and 28 have been removed and hob works including waterproof …
Progress Report Hanging stage works dealing with cavity flashings, some spalling and paint works on the Northern elevation has been extended for this next week and vehicle restrictions and access …
Hamilton’s Lift Service has been to check the lift. A part is needed to repair an inverter on the control board. Hamilton’s are attempting to source from their warehouse tomorrow. …
The Lift is Not working this morning. Suspect due to storm damage from last night. Hamilton’s Lift Service has been requested. Thanks to Paddy (Unit 38) for alerting us. Pamela MuirSecretary …
Progress Report All spalling, screeding, brick cavity and membrane works are completed for all affected Southern Balcony (2-bed) units. Work is progressing from the top down. Affected Units 39, 36, …
Week(s) Ahead An increase in manpower by builders Fluid BS means that tiling, door removal and hob works for ALL affected Southern Balcony (2-bed) units will be accelerated, beginning with …
Progress summary Further works planned (weather permitting) A reminder that the swinging stages are required to be landed overnight and on weekends. Garages for Units 2, 10, 21 and 36 …
Update on works affecting garages in clothesline area, beginning Thurs Feb 2nd. All being well (weather; scaffolder availability), the swinging stages will be moved around to the east face of …