Lift Renovation Schedule
TENTATIVE START 23 AUGUST 2024 Hamiltons recently let us know that our lift renovation is now planned from August 23 to October 26. We should have these dates confirmed by the …
TENTATIVE START 23 AUGUST 2024 Hamiltons recently let us know that our lift renovation is now planned from August 23 to October 26. We should have these dates confirmed by the …
Remaining Works Through July PaintingPainting will continue throughout July, weather permitting. This coming week please be aware and careful of painters working in the B1 and B2 parking areas, as …
Painting Painting will continue throughout July, weather permitting. This coming week please be aware and careful of painters working in the B1 and B2 parking areas.There will be no restrictions …
Progress ReportRoof Waterproofing Works Further water shutdowns are scheduled for individual elevations from 9.00am to approximately 3.30-4.00pm this week. They are: Wednesday 28th June Southern Elevation (Units 3, 6, 9,12, …
Progress ReportFront Entry Soffit (Ceiling) StatusGrinding back of multiple layers of paint and render, and significant concrete spalling rectification works have now been completed. Re-rendering of ceiling will begin tomorrow …
Progress Report Eastern (3-bed) Elevation Tiling and silicone sealing of all affected balconies is now completed. All additional brick cavity wall ties have now been installed. Eastern (3-bed) Elevation and Southern …
Progress Report Southern (2-bed) Elevation FINAL INSPECTION: Steve Bowen, supervising contractor Sutech, will undertake a final inspection of the southern elevation (2-bed) balconies tomorrow (Monday 1 May), between 9.30am and …
Progress Report Southern (2-bed) Elevation Tiling of Southern (2-bed) Elevation affected balconies is proceeding quickly and by tomorrow, Monday, will be close to starting on the 6th floor (Unit 18). …
Progress Report Painting of the Southern (2-bed) Elevation to be completed this coming week, with some balcony touch-ups to be addressed. All garages in the B2 clothesline area are currently …
Progress Report Painting of the Southern (2-bed) Elevation is well underway and continues this coming week. Door removals on affected balconies on the Eastern (3-bed) Elevation are proceeding according to …