REMAINING WORKS: SUN 9 July 2023

Remaining Works Through July PaintingPainting will continue throughout July, weather permitting. This coming week please be aware and careful of painters working in the B1 and B2 parking areas, as …

REMAINING WORKS: SUN 2 July 2023

Painting Painting will continue throughout July, weather permitting. This coming week please be aware and careful of painters working in the B1 and B2 parking areas.There will be no restrictions …

MAJOR WORKS UPDATE: SUN 25 June 2023

Progress ReportRoof Waterproofing Works Further water shutdowns are scheduled for individual elevations from 9.00am to approximately 3.30-4.00pm this week. They are: Wednesday 28th June Southern Elevation (Units 3, 6, 9,12, …

MAJOR WORKS UPDATE: SUN 4 June 2023

Progress ReportFront Entry Soffit (Ceiling) StatusGrinding back of multiple layers of paint and render, and significant concrete spalling rectification works have now been completed. Re-rendering of ceiling will begin tomorrow …

MAJOR WORKS UPDATE: SUN 7 May 2023

Progress Report Eastern (3-bed) Elevation Tiling and silicone sealing of all affected balconies is now completed. All additional brick cavity wall ties have now been installed. Eastern (3-bed) Elevation and Southern …

MAJOR WORKS UPDATE: SAT 29 MAR 2023

Progress Report Southern (2-bed) Elevation FINAL INSPECTION: Steve Bowen, supervising contractor Sutech, will undertake a final inspection of the southern elevation (2-bed) balconies tomorrow (Monday 1 May), between 9.30am and …

MAJOR WORKS UPDATE: SUN 12 MAR 2023

Progress Report Painting of the Southern (2-bed) Elevation is well underway and continues this coming week. Door removals on affected balconies on the Eastern (3-bed) Elevation are proceeding according to …