Foyer Refurbishment Timelines

Foyer Project Timelines

Dear Residents,

We’d like to share a brief update following the latest advice from our contractor, Sutech, regarding the upcoming CBC works:


Project Timeline and Next Steps:

  • CBC Work Commencement:
    CBC works are likely to start shortly after May 20, 2025.    May 27 is anticipated on site start date.
    We will confirm the exact date once final scheduling is completed.
  • Finishes Selection:
    • Design options are expected from Consultant by May 26, 2025.
    • Owner survey and review will follow immediately.
    • Final finishes selections are expected to be completed by May 31, 2025.
  • Glazing Orders:
    • A measure and order of glazing items will occur shortly after finishes are confirmed.
    • Fabrication will take approximately six weeks.
    • The glazing frame colour has been confirmed as silver to match the building’s existing windows.
  • Building Access:
    • Access via the front door may be limited for up to 8 weeks once works commences.    May 27 is anticipated on site start date.
    • Further updates and instructions will be provided closer to the start date.

Thank you for your ongoing patience and cooperation as we work to deliver these important improvements.

Stay tuned
— The Strata Committee, SP3840