Revised Program: Northern Balconies

The Pines Manly

Revised 1-Jul-22
Major Works Programme 40wks Mon 16/05/22 Fri 17/02/23
Stage 3 Northern 9 Balconies
Units 2, 5, 8, 11 ,17, 23, 26 ,32, 35 10 wks Thu 23/06/22 Wed 31/08/22
Grind and detail to slabs 2 days Thu 23/06/22 Fri 24/06/22
Spalling & V cuts 2 days Mon 27/06/22 Tue 28/06/22
Cavity works 5 days Mon 27/06/22 Fri 1/07/22
Cut rigets to hob and concrete walls 5 days Mon 4/07/22 Fri 8/07/22
Grading to balconies 4 days Thu 7/07/22 Tue 12/07/22
CR25 coating to screed 2 days Wed 13/07/22 Thu 14/07/22
Membrane installation to slabs 6 days Fri 15/07/22 Fri 22/07/22
Door removal, hob works, membrane to hobs 14 days Wed 20/07/22 Mon 8/08/22
Installation of doors plus new doors to units 2, 8 , 11, 17, 32, 35 9 days Mon 1/08/22 Thu 11/08/22
Tiling to balconies 7 days Mon 8/08/22 Tue 16/08/22
Painting works 10 days Mon 15/08/22 Fri 26/08/22
Clean balconies 3 days Mon 29/08/22 Wed 31/08/22
Removal of Scaffold 10 days Mon 29/08/22 Fri 9/09/22
Stage 1 East 10 Balconies
Units 10, 14A, 16, 19, 22, 25, 28, 31, 34, 37 19 wks Mon 8/08/22 Fri 16/12/22
Install Steel frame for scaffold 4 wks Mon 8/08/22 Fri 2/09/22
Scaffold installation 15 days Mon 5/09/22 Fri 23/09/22