The Pines Manly |
Revised | 1-Jul-22 |
Major Works Programme | 40wks | Mon 16/05/22 Fri 17/02/23 |
Stage 3 Northern 9 Balconies | ||
Units 2, 5, 8, 11 ,17, 23, 26 ,32, 35 | 10 wks | Thu 23/06/22 Wed 31/08/22 |
Grind and detail to slabs | 2 days | Thu 23/06/22 Fri 24/06/22 |
Spalling & V cuts | 2 days | Mon 27/06/22 Tue 28/06/22 |
Cavity works | 5 days | Mon 27/06/22 Fri 1/07/22 |
Cut rigets to hob and concrete walls | 5 days | Mon 4/07/22 Fri 8/07/22 |
Grading to balconies | 4 days | Thu 7/07/22 Tue 12/07/22 |
CR25 coating to screed | 2 days | Wed 13/07/22 Thu 14/07/22 |
Membrane installation to slabs | 6 days | Fri 15/07/22 Fri 22/07/22 |
Door removal, hob works, membrane to hobs | 14 days | Wed 20/07/22 Mon 8/08/22 |
Installation of doors plus new doors to units 2, 8 , 11, 17, 32, 35 | 9 days | Mon 1/08/22 Thu 11/08/22 |
Tiling to balconies | 7 days | Mon 8/08/22 Tue 16/08/22 |
Painting works | 10 days | Mon 15/08/22 Fri 26/08/22 |
Clean balconies | 3 days | Mon 29/08/22 Wed 31/08/22 |
Removal of Scaffold | 10 days | Mon 29/08/22 Fri 9/09/22 |
Stage 1 East 10 Balconies | ||
Units 10, 14A, 16, 19, 22, 25, 28, 31, 34, 37 | 19 wks | Mon 8/08/22 Fri 16/12/22 |
Install Steel frame for scaffold | 4 wks | Mon 8/08/22 Fri 2/09/22 |
Scaffold installation | 15 days | Mon 5/09/22 Fri 23/09/22 |