Following Monday’s site meeting with the Pines SC, Fluid and Sutech, here’s the current status:
- FBS are 16 days behind on the Stage 1 works due to poor weather impacting the project.
- Current works
All balconies graded and membraned.
Door replacement occurring in Units 23, 32 and 35. Remaining door works to follow in due course.
Cavity membrane works being completed.
Concrete spalling and painting works being completed on the western façade.
Ongoing noisy works should have subsided with sporadic noise only being expected. - Program for the remainder of the building will be better understood and confirmed once
FBS have finalised the scaffold design for the eastern and southern balconies and southern brickwork. - FBS have advised that noise is likely to extend from September to November for scaffold install, southern cavity works and demolition on balconies on the Stage 2 and 3 balconies.
Pines AGM 2022 Advance Notice:
Thursday 29 September 2022 at 6pm in the Meeting Room.
Chair Strata Committee SP3840