STRATA COMMITTEE 2023

At the recent Pines AGM, the SC positions were filled as follows: Chair:  Rob Muir  Secretary:  Pamela Muir Treasurer:  David Park  Committee Members:  Brian Pilbeam

Pines Services Page Updated

Our website page with a list of tradespersons who are familiar with The Pines was updated this week. These trades people have had their qualifications and insurances approved by the …

Lift Maintenance Tues 27 June

Lift Unavailable Tuesday Morning June 27 (1.5 hours) The never-ending saga of the Lift auto dialler replacement continues, due to three (!!!) postponements (illness; emergencies etc.) It will now be offline …

MAJOR WORKS UPDATE: SUN 25 June 2023

Progress ReportRoof Waterproofing Works Further water shutdowns are scheduled for individual elevations from 9.00am to approximately 3.30-4.00pm this week. They are: Wednesday 28th June Southern Elevation (Units 3, 6, 9,12, …

Lift Maintenance Thurs 22 June

Lift Unavailable Thursday Afternoon (1.5 hours) The Lift will be offline for about one and a half hours this coming THURSDAY June 22 from around 1.30pm. This is to allow installation …

Lift Maintenance Fri 16 June

LIFT OUT NEXT FRIDAY 16 JUNE 2023 At last, the autodialler part is available and will be replaced in our lift on Friday 16 June. The lift will be off-line from around …

MAJOR WORKS UPDATE: Driveway Interruptions

Parking/Driveway Interruptions Tomorrow Wednesday 7June Tomorrow, Wednesday, the hanging stages will be moved from the clothesline area around to the B1 apron and platform, to be assembled for painting works …

MAJOR WORKS UPDATE: SUN 4 June 2023

Progress ReportFront Entry Soffit (Ceiling) StatusGrinding back of multiple layers of paint and render, and significant concrete spalling rectification works have now been completed. Re-rendering of ceiling will begin tomorrow …