Major Works Update
WEEK AHEAD 17th-21st OCT, 2022 WEATHER PERMITTING! IMPACT ON B1 GARAGES ACCESS, MONDAY TO FRIDAY:Construction of the steel platform is now complete. This coming week, weather permitting, Fluid will be …
WEEK AHEAD 17th-21st OCT, 2022 WEATHER PERMITTING! IMPACT ON B1 GARAGES ACCESS, MONDAY TO FRIDAY:Construction of the steel platform is now complete. This coming week, weather permitting, Fluid will be …
This week, Fluid started building the steel frame to support the scaffolding for the Southern Balconies.
WEEK AHEAD 10 -16TH OCT, 2022 WEATHER PERMITTING! DRIVEWAY AND GARAGE ACCESS IMPACTS: Tuesday 11th: Hoist to be moved (2-3 days) to B1 level. Thursday 13th or Friday 14th: Start to build …
Civil Fire is conducting the annual inspection on Wednesday November 2. Residents will be initially contacted between 7 – 9 am. Please do NOT ignore the request since failure to …
At the recent Pines AGM, the SC positions were filled as follows: Chair: Rob Muir Secretary: Pamela Muir Treasurer: David Park Committee Members: Brian Pilbeam, Diana Mrkusich
As a professional window cleaning and after builders cleaning company, we are required to continually work with glass suppliers to ensure we are up to date with the latest glass …
Our Annual General Meeting will be held Thursday 29 September 2022 at 6pm in the Meeting Room. This is an in-person meeting. eVoting is NOT available via the Pines Website …
Pines Major Works Progress Report Sutech have provided the following progress report: Program Overview Weather Days: Two weather days have been recorded in the last two weeks. We are 18 …
Pines Major Works Progress Report Sutech have provided the following progress report: Program Overview ▪ Northern balconies- All preliminary and membrane works on the northern balconies are complete. Works are …
Following Monday’s site meeting with the Pines SC, Fluid and Sutech, here’s the current status: FBS are 16 days behind on the Stage 1 works due to poor weather impacting the …