MAJOR WORKS UPDATE: SUN 22 JAN 2023

Update on works affecting garages in clothesline area, beginning Thurs Feb 2nd.

All being well (weather; scaffolder availability), the swinging stages will be moved around to the east face of the 2-bed northern units on Thursday 2nd February. This is to enable spalling and painting works to be completed on the face of the northern balconies and adjoining walls.

The swinging stages are required to be landed overnight and on weekends.

Garages for Units 2, 10, 21 and 36 will not be able to be accessed, or vehicles enter or exit these garages at any time during the period of proposed works due to the landing of stages overnight and the risk of falling debris while works are completed overhead during work hours.

It is anticipated that this work will take approximately three weeks.

Vehicles in garages 15, 14A and 24 will not be able to enter or exit during work hours of 7am-3.00pm weekdays for the same period, due to the risk of falling debris.

All other vehicles are prohibited due to the risk of falling debris.

Use of the clothesline is ill-advised during this time due to the risk of falling debris and flying dust damaging clothes. Access to the clothesline will be restricted to passage through the B2 garages and then round the back garden only.

Vehicles in garages 14A and 24 should prepare for similar 24-hour restrictions and will be advised when the landing stages are moved to their side of the building.

Vehicle access to garages and driveway in the weeks ahead.

There will be multiple deliveries occurring through the weeks ahead as balcony screeding, membrane and tiling goes ahead.

Residents are reminded to always allow time to check for delivery truck obstructions on the driveway and B1 platform area before driving out or in, and to be patient. Fluid will make access available as soon as they can.

Thank you,
Pamela Muir, Secretary
Strata Committee SP3840