MAJOR WORKS UPDATE: SUN 12 MAR 2023

Progress Report

Painting of the Southern (2-bed) Elevation is well underway and continues this coming week.

Door removals on affected balconies on the Eastern (3-bed) Elevation are proceeding according to schedule (see below).

All garages in the B2 clothesline area are currently accessible until further notice, as is the clothesline. This will change when the hanging stage is repositioned for painting and spalling works on the Eastern Elevation.


Week Ahead

Door removal will begin tomorrow for Units 16, 14A and 10. Affected residents are requested to move furniture, paintings and ornaments at least one metre away from their doors prior to the start date of these works.

Affected residents are requested to leave their sliding doors unlocked for the duration of works scheduled for their unit.

Affected residents are also requested to remove blinds and curtains if possible. Please be aware that once removed, existing blinds and curtains may need to be altered to fit.

Once doors are removed, openings will be boarded up. Subject to any delays (weather, access, difficulties with particular doors), it is anticipated that each affected unit will take up to 7 days to complete the necessary hob rebuilding/waterproofing and door replacement work.

Door replacement for Units 25, 22 and 19 will take place during the week. Please check the schedule:

Balcony Tiling

Balcony tiling will not take place until the cleaning and painting of internal balcony (painted) surfaces is completed after doors are replaced. This is to avoid any damage to the new tiles.