Major Works 2022 Schedule: 16 May Start

A substantial revision of the Major Works program means that work can commence in approximately four weeks. The change allowing this to happen is that work starts on the Northern Elevation, rather than the Southern Elevation as originally proposed. The complex scaffolding required for the Southern Elevation would have taken an additional 6 weeks to construct, and rather than continue to hold off for this, the SC has taken the decision to start with the Northern Elevation and have this work proceed while the Southern scaffolding is being engineered. Accordingly,  Fluid have now provided us with a revised work schedule. Work will now begin on May 16. Please refer to the picture below for location codes.

The Pines Manly Revised 13-Apr-22
Total Major Works Programme 40wks Mon 16/05/22 Fri 17/02/23
Site set up 5 days Mon 16/05/22 Fri 20/05/22
Stage 3 Northern 9 Balconies
Units 2, 5, 8, 11 ,17, 23, 26 ,32, 35 15 wks Mon 16/05/22 Fri 26/08/22
Painting works from swing stage 14 wks Mon 23/05/22 Fri 26/08/22
Stage 1 Eastern 10 Balconies
Units 10, 14A, 16, 19, 22, 25, 28, 31, 34, 37 19 wks Mon 1/08/22 Fri 9/12/22
Stage 2 Southern 11 Balconies
Units 3, 9, 15, 18, 21, 24, 27, 30, 33, 36, 39 17 wks Mon 29/08/22 Fri 23/12/22
Cavity Flashing Works 13 wks Mon 26/09/22 Fri 23/12/22
Roof Membrane Works 6 wks Mon 9/01/23 Fri 17/02/23
Source: Fluid 13Apr22

Thank you for your consideration.