Major Works 2022 Revised Schedule

Sutech/Fluid have now provided us with a revised work schedule. Please refer to the picture below for location codes.

The previous program suggested a start date of mid-March. However, due to COVID and all the wet weather, this has been moved back to April 4.

Fluid are still optimistic for a Christmas finish, but that will depend on whether Fluid encounters any other delays along the way.

The Pines Manly

Revised 4-Feb-22

Total Major Works Programme

40 wks Mon 4/04/22 Fri 6/01/23
Site set up 5 days  Mon 4/04/22  Fri 8/04/22
Painting works from swing stage/ rope access 12 wks  Mon 11/04/22  Fri 1/07/22

Stage 1 Eastern: 10 Balconies

Units 10, 14A, 16, 19, 22, 25, 28, 31, 34, 37 17 wks Mon 4/04/22 Fri 29/07/22
Scaffold installation Stages 1 & 2 9 days Mon 4/04/22 Thu 14/04/22

Stage 2 Southern: 11 Balconies

Units 3, 9, 15, 18, 21, 24, 27, 30, 33, 36, 39 17 wks Mon 2/05/22 Fri 26/08/22
Removal of Scaffold Stages 1 & 2 / Cleaning 7 days Thu 18/08/22 Fri 26/08/22

Stage 3 Northern: 9 Balconies

Units 2, 5, 8, 11 ,17, 23, 26 ,32, 35 15 wks Mon 22/08/22 Fri 2/12/22
Scaffold installation Stage 3 5 days Mon 22/08/22 Fri 26/08/22
Removal of Scaffold Stage 3 / Cleaning 5 days Mon 28/11/22 Fri 2/12/22
Cavity Flashing Works 10 wks Mon 18/04/22 Fri 24/06/22
Roof Membrane Works 8 wks Mon 14/11/22 Fri 6/01/23

Thank you for your consideration.