Sutech/Fluid have now provided us with a revised work schedule. Please refer to the picture below for location codes.
The previous program suggested a start date of mid-March. However, due to COVID and all the wet weather, this has been moved back to April 4.
Fluid are still optimistic for a Christmas finish, but that will depend on whether Fluid encounters any other delays along the way.
The Pines Manly |
Revised | 4-Feb-22 | |
Total Major Works Programme |
40 wks | Mon 4/04/22 | Fri 6/01/23 |
Site set up | 5 days | Mon 4/04/22 | Fri 8/04/22 |
Painting works from swing stage/ rope access | 12 wks | Mon 11/04/22 | Fri 1/07/22 |
Stage 1 Eastern: 10 Balconies |
|||
Units 10, 14A, 16, 19, 22, 25, 28, 31, 34, 37 | 17 wks | Mon 4/04/22 | Fri 29/07/22 |
Scaffold installation Stages 1 & 2 | 9 days | Mon 4/04/22 | Thu 14/04/22 |
Stage 2 Southern: 11 Balconies |
|||
Units 3, 9, 15, 18, 21, 24, 27, 30, 33, 36, 39 | 17 wks | Mon 2/05/22 | Fri 26/08/22 |
Removal of Scaffold Stages 1 & 2 / Cleaning | 7 days | Thu 18/08/22 | Fri 26/08/22 |
Stage 3 Northern: 9 Balconies |
|||
Units 2, 5, 8, 11 ,17, 23, 26 ,32, 35 | 15 wks | Mon 22/08/22 | Fri 2/12/22 |
Scaffold installation Stage 3 | 5 days | Mon 22/08/22 | Fri 26/08/22 |
Removal of Scaffold Stage 3 / Cleaning | 5 days | Mon 28/11/22 | Fri 2/12/22 |
Cavity Flashing Works | 10 wks | Mon 18/04/22 | Fri 24/06/22 |
Roof Membrane Works | 8 wks | Mon 14/11/22 | Fri 6/01/23 |
Thank you for your consideration.