Steel Scaffolding Frame Takes Shape
This week, Fluid started building the steel frame to support the scaffolding for the Southern Balconies.
This week, Fluid started building the steel frame to support the scaffolding for the Southern Balconies.
WEEK AHEAD 10 -16TH OCT, 2022 WEATHER PERMITTING! DRIVEWAY AND GARAGE ACCESS IMPACTS: Tuesday 11th: Hoist to be moved (2-3 days) to B1 level. Thursday 13th or Friday 14th: Start to build …
Pines Major Works Progress Report Sutech have provided the following progress report: Program Overview Weather Days: Two weather days have been recorded in the last two weeks. We are 18 …
Pines Major Works Progress Report Sutech have provided the following progress report: Program Overview ▪ Northern balconies- All preliminary and membrane works on the northern balconies are complete. Works are …
Following Monday’s site meeting with the Pines SC, Fluid and Sutech, here’s the current status: FBS are 16 days behind on the Stage 1 works due to poor weather impacting the …
Subject to suitable weather conditions, particularly wind, painters will begin work Monday 22/8 on the WESTERN face of the Pines. This is the side facing The Crescent. ALL Owners and …
Subject to suitable weather conditions, particularly wind, painters will begin preparation work Monday 15/8 on the WESTERN face of the Pines. This is the side facing The Crescent. ALL Owners …
Screeding of affected balconies on the Northern elevation has been completed and prepping for the waterproof membrane has begun.Fluid Building Services/Sutech have advised that residents should expect balcony door removal …
Progress Report:Fluid reports that we are now 16 days behind on the Stage 1 (Northern) works due to poor weather impacting the project (this July being the wettest ever recorded!). …
We made an attempt to continue here on site but unfortunately the weather is again no good – high winds and driving rain directly onto balconies. We’ll make another attempt …