MAJOR WORKS UPDATE: SUN 5 MAR 2023
Progress Report Cavity flashing works on the Eastern (3-bed) façade are 100% complete.Affected Eastern balcony doors for Units 34, 31 and 28 have been removed and hob works including waterproof …
Progress Report Cavity flashing works on the Eastern (3-bed) façade are 100% complete.Affected Eastern balcony doors for Units 34, 31 and 28 have been removed and hob works including waterproof …
Progress Report Hanging stage works dealing with cavity flashings, some spalling and paint works on the Northern elevation has been extended for this next week and vehicle restrictions and access …
Progress Report All spalling, screeding, brick cavity and membrane works are completed for all affected Southern Balcony (2-bed) units. Work is progressing from the top down. Affected Units 39, 36, …
Week(s) Ahead An increase in manpower by builders Fluid BS means that tiling, door removal and hob works for ALL affected Southern Balcony (2-bed) units will be accelerated, beginning with …
Progress summary Further works planned (weather permitting) A reminder that the swinging stages are required to be landed overnight and on weekends. Garages for Units 2, 10, 21 and 36 …
Update on works affecting garages in clothesline area, beginning Thurs Feb 2nd. All being well (weather; scaffolder availability), the swinging stages will be moved around to the east face of …
Internal Door Hob Finishes and Door Replacement To confirm previous advice, costs associated with Internal Hob Finishes and New Door Replacement are for the account of individual owners. Due to …
THEY’RE BA-AACK! Construction site conditions have resumed after the Christmas/New Year Break. Access: Residents are reminded that, while there are currently no restrictions on driveway access and garaging, please always …
Demolition of all nominated balconies on the eastern and southern drops have been completed. The top six levels of cavities are underway. Spalling is completed on the southern balconies. Eastern …
SUSPENSION OF WORKS DURING THE CHRISTMAS/NEW YEAR HOLIDAY BREAK WEDNESDAY 30 NOVEMBER 2022 The Pines construction site will be shut down between 23rd December – 9th January 2023 as this …